Project: BMW Group

Location: Washington, DC

This project was the build-out of a core and shell space for the Government Affairs Office of BMW. The build-out addressed putting a host of new utilities in a limited ceiling space, around and through existing drywall and exposed ceilings in an occupied space below. Close coordination of all utilities was required to install the specialty ceiling system and movable glass wall assembly. All offices were erected with glass storefronts and Herculite doors. The major challenge of the project was to complete the work in 10 weeks with a 8 week lead time on the glass movable partition assembly. Delivering the space as planned required that we work to allow the owner’s furniture vendor to set materials prior to substantial completion.